Moving or closing an office: what to do with the IT equipment

The IT is usually the last thing anyone plans and the first thing that goes wrong, because it's tangled up with the lease, the phone lines, the landlord's reinstatement clause and a deadline that doesn't move. Here's the version that works backwards from the day you hand back the keys.

The short version

  1. Work backwards from the handover date, not forwards from today. Collection slots and disconnection notice periods are the constraints.
  2. Sort everything into four piles early: goes with us, gets sold, gets destroyed, belongs to someone else.
  3. Check the lease for a reinstatement clause. Cabling and racks you installed often have to come out, at your cost.
  4. Leased and financed equipment is not yours to dispose of. Mixing it into the disposal pile is an expensive mistake.
The plan

Working backwards from handover day

01Fix the real deadline

Not the move date — the date the space must be empty and reinstated. Everything else schedules against it. Then subtract a week, because something always slips.

02Walk the building and list everything

Including the places nobody thinks of: the comms cupboard, the ceiling void, the reception desk, the warehouse office, the copier room. Record what's there and photograph it. Building the asset list.

03Separate out what isn't yours

Leased IT, financed hardware, the landlord's fixtures, the copier on a service contract, the alarm and CCTV, carrier-owned routers. Each has its own return process and its own penalty for getting it wrong. Lease returns.

04Give notice on lines and circuits

Internet, phone, and any dedicated circuits. Notice periods of 30 to 90 days are normal and billing continues until they expire regardless of whether you've moved. This is the one that most often gets missed.

05Decide what actually travels

A move is a good moment to retire equipment rather than pay to transport it twice. Anything five years or older is usually cheaper to replace at the other end than to move, insure and re-rack.

06Get the disposal pile valued

Send the list before you commit, because the gap between scrap value and resale value on servers and recent laptops is usually significant and it offsets the cost of the move.

07Handle the data before the chaos

Equipment goes missing during moves — it's the single most common time for it. Destroy or wipe what isn't travelling while the building is still orderly, and get the certificate before boxes start moving.

08Strip out what the lease requires

Structured cabling, racks, wall-mounted brackets, server room air conditioning, badge readers. Reinstatement clauses are routinely enforced and the bill for the landlord doing it for you is never the cheap option.

09Collect the paperwork in one place

Destruction certificates, lease return confirmations, disconnection confirmations, the disposal settlement. For a closure in particular, somebody will ask for these months later when the entity is already wound down.

What catches people

The expensive surprises

Straight talk

When you don't need us for this

Questions

Questions about office moves and closures

What should we do with IT equipment when closing an office?

Separate it into four groups first: equipment going to another site, equipment to be sold, equipment to be destroyed, and equipment that belongs to someone else such as leased hardware and carrier routers. Deal with the data on anything leaving your control before the move begins, because moves are when equipment goes missing. Then get the disposal pile valued, as servers and recent laptops often cover a meaningful part of the move cost.

How far in advance should we arrange IT disposal for an office move?

Start four to six weeks before the handover date for a typical office. The physical collection takes a day, but circuit disconnection notice periods run 30 to 90 days, lease returns have their own deadlines, and building access for a large collection often needs arranging a week or more ahead. Working backwards from the date the space must be empty is more reliable than working forwards.

Who is responsible for removing cabling and racks when a lease ends?

Usually the tenant, under a reinstatement or make-good clause. Many commercial leases require the space to be returned to its original condition, which covers structured cabling, racks, wall brackets and sometimes server room air conditioning. Read the clause early, because the landlord arranging the work and billing you is invariably more expensive than doing it yourself.

Can you collect everything in one visit during a move?

Usually yes, if we know what is coming. Send the asset list in advance so the right vehicle and crew are scheduled, and tell us about access constraints such as loading dock times, lift bookings or out-of-hours restrictions. For larger sites we can also destroy drives on-site during the same visit so nothing readable leaves the building.

What happens to equipment that has no resale value?

It is recycled responsibly rather than dumped, and that should be part of the same collection at no extra cost on a load with some value in it. You should receive documentation covering the recycled items as well as the ones you were paid for, because the environmental record matters for the same audits as the data record.